A modular water injection station (MWIS) for Yuganskneftegaz has been commissioned

1 May 2019

The commissioning and supervision installation service of joint-stock company OZNA completed commissioning of a modular water injection station (MWIS) at KNS-3 (Water Injection Station-3) in Ombinskoye Field of Rosneft-Yuganskneftegaz Oil Company. 

Ombinskoye Field is one of the most promising in Yugansneftegaz. It is equipped with facilities for oil collection, pumping, treatment and transportation, providing an average daily production of more than nine thousand tons of oil. Today the important part of oilfield infrastructure is a modular water injection station (serial No. 78) with five centrifugal pumps TsNS240-1900 and the required life support system.